Rehabilitation of the section PK82-PK117


On this section, the aim was to reform the road from the base layer over 4.5 km in length and improvement of the width of the road (before rehabilitation l: 7m after rehabilitation l: 10m)
The works carried out are:

  • Scarification of the existing asphalt and the base layer
  • Implementation of a new 0 / 31.5 base layer
  • Adjustment and compaction
  • Implementation of the impregnation layer
  • Implementation of the first wearing course in Grave bitumen of 0/20, th. : 7cm
  • Implementation of the tack coat
  • Implementation of the second asphalt concrete wearing course, th. : 5cm

    PK112-PK117

    Rehabilitation

    ADR

Progress
General Progresss
100%
Phase 1
100%
Phase 2
100%